Vessel maintenance
Planned maintenance for small passenger vessels and ferries: building a system that stands up to survey
A planned maintenance system should include every job your vessel needs, how often each task should be done, who completed it, and what was found. Keeping these records helps you prove the work was carried out. The safety management codes do not require a specific format, but they do expect equipment to be maintained and inspected regularly, usually following the manufacturer's guidance, with records to show it. Your system is ready for a survey when a surveyor can pick any item on board and you can show its last service, the next due date, and any defects found.
This guide explains what the rules require, how to set up a system for a small passenger boat or ferry, and what surveyors and auditors expect to see.
What the rules require
ISM Code, Element 10. For vessels under ISM, the company must have procedures to ensure the ship is maintained in conformity with the relevant rules and regulations. It must also report non-conformities with their possible cause, and identify in the SMS the equipment and technical systems whose sudden failure could cause a hazardous situation. IACS Rec. 74 is industry guidance on how to manage maintenance to meet those requirements.
Domestic Safety Management (DSM) Code. Most UK domestic passenger ships (Classes III to VI(A)) are under the DSM Code rather than the ISM Code. MGN 536 Amendment 5 is the MCA's guidance on the Code, and the MCA's instructions to its surveyors (MSIS 29) show how compliance will be assessed. They say equipment on board all vessels should be maintained and inspected. The operator sets the intervals, but they should follow the manufacturer's procedures. At audit, the surveyor expects to see on-board maintenance checklists and all other maintenance and repair records, including work done by shore contractors.
Certificates and surveys. UK domestic passenger certificates are issued for no more than 12 months (MIN 500), so the survey cycle is annual. Under the Workboat Code Edition 3, a certificate is valid for no more than five years. Within that cycle the vessel has an annual examination by an authorised person, an intermediate examination (normally out of the water) and a renewal examination out of the water before the certificate expires. The hull, shell fittings and external steering and propulsion must be examined out of the water at intervals not exceeding three years. RIBs and inflatable boats also need an airtightness test every year. A certificate stops being valid if the annual or intermediate examination isn't completed in time.
The Workboat Code's safety management system appendix is explicit about maintenance: the operator must have documented inspection and maintenance procedures, sets the frequency, and must record all inspection and maintenance activities.
None of these codes gives you a form to complete. They expect a system that fits your vessel and records that prove it works.
The building blocks of a planned maintenance system
A small ferry does not need complicated fleet software made for tankers. It only needs five connected parts.
- An equipment register. Every item that needs maintaining: main and auxiliary engines, gearboxes, steering, bilge pumps and alarms, fire detection and extinguishing, navigation lights, radios, liferafts, lifejackets, gangways, ramps and mooring gear. Note the make, model, serial number and location.
- A task list for each item. Write down what needs to be done and how often, either by calendar date or running hours. Start with the manufacturer's manual, then add tasks based on your own experience or past problems.
- A schedule. Include daily and pre-departure checks, weekly tests, monthly and yearly tasks, and any shore-based work related to refits and slipping.
- Records of finished work. Write down who did the job, when it was done, what was found, and any parts used. Also include job sheets and certificates from shore contractors.
- A defect process. It should let you report a fault, decide if the vessel can still operate, fix the problem, and confirm it is sorted out (more below).
Keep daily checks short. A pre-departure checklist that takes five minutes is more likely to be done properly. If it is too long, people might just tick boxes without really checking.
Link running hours to maintenance tasks. It is easy to miss hours-based engine services during busy times. Log engine hours at least once a week so you know when jobs are due before they get missed.
Critical equipment and lifesaving appliances
Some equipment is more important because its sudden failure can put people at risk. ISM Element 10.3 calls this critical equipment. Even under the DSM Code, it is worth identifying these items.
Typical critical equipment on a small passenger vessel or ferry:
- Propulsion and steering, including emergency steering
- Bilge pumps and bilge alarms
- Fire detection and fixed firefighting systems
- Watertight doors, closures and their indicators
- Navigation lights, VHF/DSC and other radio equipment
- Ramps, gangways and their hydraulics
- Lifesaving appliances
Test critical items as well as servicing them. For example, a bilge alarm is only properly maintained if someone floats the switch and hears the alarm sound. Record the test, not just the service.
Lifesaving appliance servicing. Under MGN 548, SOLAS inflatable lifesaving appliances, including liferafts and inflatable lifejackets, must be serviced at intervals not exceeding 12 months at an approved service station. Under the Workboat Code, inflatable lifejackets are serviced within a month either side of each compliance, renewal and intermediate examination, and at least annually in between. Keep the service certificates with your maintenance records. Hydrostatic release units have their own expiry dates: record them per unit.
The MCA's service station finder on GOV.UK lists approved stations for inflatable lifesaving appliances. Use it to check your servicing agent is approved, and keep that check with your records.
Defects: reporting, deferral and close-out
A maintenance system is judged not just by how it handles routine jobs, but also by how it handles faults. Keep the defect process to four clear steps.
- Report the defect. Anyone on board should be able to report a problem quickly, ideally with a photo. If crew have to go to the office to report a fault, most won't.
- Decide what to do. The skipper or person in charge decides whether the vessel can sail, with restrictions or not at all. Report defects in critical equipment directly to the shore manager or DPA.
- Fix the problem or defer it. If you defer it, write down the reason, any temporary fixes and a target date. A deferred defect without a date is an ongoing risk.
- Close out the defect. Write down what was done, who did it, and the test that showed it worked. Then decide whether the task list needs updating to stop it happening again.
Under ISM Element 10.2 and the DSM Code, report non-conformities and their possible causes to the company. If the same defect keeps coming back, review the maintenance interval or method.
What surveyors and auditors look for
- Records that match the vessel. Surveyors will pick an item on board and ask for its maintenance history. If the paperwork does not match the serial number on the equipment, it will be marked as a problem.
- No overdue tasks without a reason. An overdue task with a recorded deferral and a date is manageable. One that was simply missed is not.
- Defects closed out properly. A fix, a test and a sign-off, not just a note saying "done".
- Contractor work recorded. Shore engineers' job sheets and LSA service certificates filed with the right equipment records.
- A system that adapts. Proof that repeated faults have led you to change the task list or the maintenance interval.
A real example
I once worked for a small charter company where the owner kept all the maintenance information in his head. After a small issue with an impeller burning out, some major items were missed during repairs. Without a written record, the oversight led to a major engine overhaul that cost thousands of pounds and kept the boat out of service for weeks.
Lessons from MAIB investigations
- Wight Sky (ro-ro passenger ferry, report 4/2022): two catastrophic engine failures. Safety issues included maintenance management and quality-control standards, and no clear ownership of engine maintenance and condition monitoring.
- Jean Elaine (dive support vessel, report 15/2025): after a grounding, the hull's poor condition likely contributed to its failure. The vessel was not certified.
- Svitzer Mercurius (tug, report 15/2022): a towline pennant broke at about 52% of its original minimum breaking load and was not fit for purpose. Five crew were injured.
- Dart 8 (ro-ro, report 12/2004): abrasion had reduced a mooring rope's breaking load by 87.7%. The MAIB said ropes should be inspected under a planned maintenance system.
The common problem: equipment was not checked or managed in a way that caught its decline before it failed. Ropes, hulls and engines all wear out over time, and a planned maintenance system is how you spot the trend early.
Quick checklist
- Equipment register lists every maintainable item, with serial numbers
- Each item has tasks and intervals based on the manufacturer's manual
- Critical equipment is identified and tested, not just serviced
- Running hours are logged at least weekly
- LSA service certificates and expiry dates are recorded per item
- Defects are raised, decided, fixed or deferred with a date, and closed out with a test
- Shore contractor job sheets are filed against the right item
- Repeated defects trigger a review of the task or interval
How Helmsman helps
Helmsman keeps your maintenance, defects and inspection records in one place per vessel, so when the surveyor points at an item, you can show its history in seconds:
- Tasks missed in a busy season. Vessel maintenance schedules by date or running hours, with due and overdue flags per vessel.
- Records that don't match the vessel. An equipment register per vessel, so every service, defect and certificate is filed against the right item.
- Defects raised verbally and forgotten. Defect reporting from a phone with photos, a sail / restrict / don't-sail decision, deferral dates and close-out sign-off.
- Expired liferaft or lifejacket servicing. Lifesaving equipment records with service and expiry dates, and reminders before they lapse.
- Daily checks done on paper and lost. Pre-departure and vessel inspection checklists completed on board and stored with the vessel record.
FAQs
Is a planned maintenance system a legal requirement for small passenger vessels?
The codes don't require a particular system. Under the ISM Code and the DSM Code, equipment must be maintained and inspected, and you must keep records. A planned maintenance system is the practical way to show that.
What maintenance intervals should I use?
Start with the manufacturer's intervals. The MCA's DSM guidance says operators set the intervals but should follow the manufacturer's procedures. Shorten them for anything that has failed before or works hard.
How often must liferafts and lifejackets be serviced?
Under MGN 548, SOLAS inflatable lifesaving appliances must be serviced at intervals not exceeding 12 months at an approved service station. Check the rules for your vessel's code.
What is critical equipment?
Equipment whose sudden failure could cause a hazardous situation, such as steering, propulsion, bilge alarms and firefighting systems. ISM Element 10.3 requires it to be identified in the SMS.
What do surveyors look for in maintenance records?
Records that match the equipment on board, nothing overdue without a recorded reason, defects closed with a test, and contractor work and service certificates on file.
Can I defer a defect?
Yes, if the vessel is safe to operate. Record the reason, any temporary measures, any restrictions and a target date, and make sure the shore manager or DPA has agreed it.
Sources
- IACS Rec. 74: A guide to managing maintenance in accordance with the ISM Code
- MGN 536 (M) Amendment 5: Safety management code for domestic passenger ships
- MSIS 29: Domestic Safety Management Code, instructions for surveyors
- MIN 500: Passenger ships, five-year certificates, change in policy
- The Workboat Code Edition 3
- MGN 548 (M+F) Amendment 1: servicing of SOLAS inflatable lifesaving appliances
- MAIB reports linked in the lessons section above
Helmsman runs this six-stage process for you — capture to close-out, with the records joined up so they survive an audit.
Join the waitlistAbout this guide. Written by John Wilmans, a working skipper who has been through a domestic safety management audit from the side of the operator being audited.Reviewed by John Wilmans on 13 October 2026.
This guide is general information, not legal advice, and it describes United Kingdom (MCA) — ISM Code, Domestic Safety Management (DSM) Code, Workboat Code Edition 3. Requirements differ between flag states and administrations — always confirm with your own flag state or administration. Spotted something wrong?Tell me and I'll correct it.